Los Osos · 2026 guide
Building in Los Osos.
The moratorium held new houses in Los Osos from 1988 to October 29, 2024. The County now reviews new homes through a yearly allocation and habitat-coverage process.
This page is what a new house on a Los Osos lot needs in 2026: the growth allocation, the habitat certificate, and the permits, in the County's own order. Checked October 27, 2026.
We have built in Los Osos since 1983, from an office on 1191 4th Street. We know the County set and the lots.
Schedule a ConsultationLocal coverage · KSBY
Crizer in the Community
Los Osos couple gets closer to building their dream home after 50-year wait (opens on KSBY in a new tab)
KSBY spoke with Sam Crizer and Matt Davis about a Los Osos couple’s plans to build after a 50-year wait.
Read the KSBY report (opens in a new tab)What changed.
The freeze protected the Los Osos groundwater basin, the town's only water source, until the sewer, a basin plan, and a habitat plan were in place.
With the sewer running and the Los Osos Habitat Conservation Plan approved, the County Board of Supervisors lifted the moratorium on October 29, 2024.
Growth is still metered. Each December the County sets how many new houses the basin can carry the next year.
2026: 25 new homes.
On December 16, 2025 the County set the 2026 growth rate at 0.4 percent: 25 new units for all of Los Osos. 19 are inside the sewer service area, 12 single-family and 7 multi-family.
As of September 17, 2026, the County had issued 5 allocations and expected 15 to 20 more to open on October 1. Allocations nobody uses in 2026 carry over to 2027.
Who needs an allocation.
Every new dwelling unit inside the Los Osos Urban Reserve Line needs one. The County splits the year's units into two shares.
- Sewer service area lots
- 75 percent of the year's units
- Offered through the Waitlist-to-Build in phases: batch by batch first, then the whole waitlist, then any lot in the sewer service area.
- Outside the sewer service area, and the exceptions
- 25 percent of the year's units
- Lots outside the sewer service area, accessory dwellings, deed-restricted affordable housing, and second-story conversions of nonresidential floor area. For eligible uses in that category, complete requests are considered in arrival order between January 1 and July 1. After July 1, unused allocations are prioritized for the sewer service area. The County directs applicants in the reserved category to the next January 1. The allocation page lists accessory dwellings among the uses sharing a reserved 25 percent category. That category is not permission to build an ADU in Los Osos. The County's specific Los Osos restriction still applies.
- Work on a lot with a house
- Check the proposed use
- The allocation rule applies to new dwelling units. Existing homes, guesthouses, and ADUs have different permit requirements. Check the intended use and any habitat coverage with the County.
The 2026 calendar.
Sewer service area allocations open in three phases. The County set these dates in its February 2026 letter to waitlist owners.
01
May 1 to June 30Batch 1 only: waitlist positions 1 to 12 on the single-family list and 1 to 7 on the multi-family list.
Notified May 1. Thirty days to state an intent to apply for construction permits, then 45 more days to submit the permit application.
02
July 1 to August 1Any waitlist owner, in waitlist order.
Whatever Batch 1 did not use opens to the whole waitlist, with the same 30-day and 45-day windows.
03
October 1 to December 31Any lot in the sewer service area. First come, first served.
Waitlist position no longer matters. The construction permit application must be in by December 31. Anything still unused carries into the next year.
The habitat plan.
The Los Osos Habitat Conservation Plan covers the endangered species that live on the lots. A new house needs three things from it.
- A Certificate of Inclusion from the County.
- Compliance with the conditions of the County's Incidental Take Permit, including avoidance and minimization measures on the lot.
- Habitat plan fees, set by the total square feet of ground the project disturbs.
The County reports that all of its available 2026 habitat mitigation credits are reserved. It is accepting no additional applications for those credits in 2026 and expects more credits in early 2027. It asks owners to check again in December 2026.
New foundations, utility trenches, grading, and construction access can affect habitat coverage. Confirm the project footprint and credit availability before setting a construction date.
What the County asks for
- A Development Request Form, with the growth allocation and habitat credit boxes checked.
- Verification of water supply and wastewater treatment, sent to the County by email.
- Your waitlist position, if you have one. The County's letter is the fastest proof.
- Some lots also need a Minor Use Permit or a Coastal Development Permit. A lot check tells you which.
Vacant lot to finished house.
Five steps, in order. We carry each one, from the lot check to final inspection. See how the build itself runs on our process, and what a finished house looks like under custom homes.
01
Check the lot
Zoning, setbacks, slope, and whether the lot sits inside the sewer service area or the coastal zone. Most of the answer is in the County record before anyone draws a line.
02
Secure a growth allocation
Every new house in Los Osos needs one of the year's allocations. The County offers them to the Waitlist-to-Build first, in phases, then opens what is left to the rest of the sewer service area in October.
03
Get the habitat certificate
The Los Osos Habitat Conservation Plan covers the endangered species on the lots. A new house needs a Certificate of Inclusion and pays habitat fees based on the ground it disturbs.
04
Design and permit
Plans, a coastal development permit where the lot calls for one, and a County building permit. We draw the set, submit it, and answer the County's comments.
05
Connect and build
Sewer connection, utilities, and construction under one name through final inspection.
Questions owners ask.
- Is the Los Osos building moratorium over?
- Yes. The County Board of Supervisors lifted it on October 29, 2024, after 36 years. Building is open again, but new houses are metered by a yearly growth rate tied to the groundwater basin.
- How many new homes can be built in Los Osos each year?
- The County sets the number each December from basin data. For 2026 it is 0.4 percent, 25 new units for the whole community, with 19 inside the sewer service area: 12 single-family and 7 multi-family. As of September 17, 2026, five had been issued, and the County expected 15 to 20 more to open on October 1.
- I am on the Waitlist-to-Build. What happens now?
- The County offers allocations to the waitlist in phases, in waitlist order, and writes to owners when their batch opens. In 2026 only Batch 1 was notified, on May 1. Any waitlist owner could request an unused allocation from July 1. Bring your County letter to a consultation and we will plan around your date.
- I own a vacant lot but I am not on the waitlist. Can I build?
- Possibly. From October 1 through December 31, any unused allocation opens to any lot in the sewer service area, first come, first served, as long as the construction permit application is in by December 31. Unused 2026 allocations carry over to 2027. A lot check tells you what the lot needs first, so you are ready when allocations open.
- If I miss my batch, do I lose my place on the waitlist?
- No. The County says not responding, or not submitting permits, does not remove a property's waitlist position for future allocations.
- Do ADUs and guesthouses need an allocation?
- The County currently prohibits ADUs in Los Osos under its coastal land use ordinance. Its Los Osos FAQ says the Board of Supervisors may revisit the restriction. The growth allocation applies to new dwelling units. A guesthouse has a different use and permit path; the County must confirm the project requirements, including habitat coverage.
- What is a Certificate of Inclusion?
- The County document that shows a project complies with the Los Osos Habitat Conservation Plan and the County's Incidental Take Permit. A new house needs one, follows the permit's avoidance and minimization conditions, and pays habitat fees based on the square feet of ground it disturbs.
- What does it cost to build on a Los Osos lot?
- It depends on the lot and the house. Beyond construction, a new house carries habitat fees set by the disturbed area, permit fees, and a sewer connection. We price each project on a Cost Plus basis after a planning phase, so the number is real before you commit.
- What should I bring to a first meeting?
- The lot's address or parcel number, any County letter about your waitlist position or allocation, and any survey or soils report you already have. From that we can run a lot check and tell you what the lot needs before anything is drawn.
Sources
Checked October 27, 2026. The County updates these rules each year. Its pages are the final word.
- County: Los Osos development FAQ and ADU restrictions (opens in a new tab)
- County: residential growth rate allocations (opens in a new tab)
- County: habitat credits and Certificates of Inclusion (opens in a new tab)
- County: guesthouse uses and coastal ordinance reference (opens in a new tab)
- County: building permit FAQ, ADUs and guesthouses (opens in a new tab)
- County: February 25, 2026 update to waitlist property owners (opens in a new tab)
- New Times SLO: Habitat Conservation Plan approved as the moratorium lifts (opens in a new tab)